Pirganj Rural Road Upgrade (Phase 2)

Pirganj Rural Road Upgrade (Phase 2)

Rural road, culvert, and connectivity infrastructure improvement project.

Running

Sector: Infrastructure

Location: Pirganj, Rangpur-6

Implementing Agency: LGED

Current Phase: Field Implementation

Start Date: 9/1/2025

Expected End: 3/30/2027

Total Budget: BDT 32,000,000

Spent So Far: BDT 14,850,000

Progress: 46%

Beneficiaries: Approximately 125,000 citizens

Detailed Project Breakdown

The project includes union-level road reconstruction, culvert repairs, and improved connectivity to markets, schools, and health facilities.